Learn how to size a generator in kW or kVA, account for motor starting (inrush) loads, apply diversity factor, and avoid the two most common sizing mistakes: undersizing and oversizing.
A correctly sized generator runs efficiently, meets voltage and frequency under load, and lasts. A wrong size either stalls on startup or wastes fuel and capital. This guide shows the calculation we use for real installations.
Write down every device the generator must supply, with its running power in watts or kW. Include lighting, HVAC, pumps, compressors, servers and any motor-driven equipment.
Electric motors draw a large inrush current at startup — often 3x to 7x their running load for a few seconds. A 2 kW compressor may need 10 kW to start. Size for the largest simultaneous starting surge, not just the steady sum.
Not every load runs at once. A diversity (or coincidence) factor of 0.6–0.8 is common for buildings. Multiply the total by this factor to avoid gross oversizing — but never apply it to critical simultaneous loads.
Generators are often rated in kVA. Use: kVA = kW ÷ power factor (typically 0.8). A 100 kW load at 0.8 pf needs 125 kVA.
Specify roughly 20–25% spare capacity above the calculated peak. This covers future expansion, derating at altitude/high temperature, and ageing.
Small sites (homes, shops) use single-phase 220–240V. Industrial sites use three-phase 380–415V. Match the generator to your distribution.